Union Pacific Railroad – Tunnel #17 Rehabilitation

This was mostly an unlined natural rock tunnel with 33 feet at the north end of the tunnel being supported by timber sets. This line carries single mainline track in a north/south direction. The tunnel is approximately 428 feet long, 20 feet wide, and 25 feet tall....

Johnson City Culvert Project

Removed damaged area of existing CMP and reconstructed tunnel with steel ring beams and spilling. Back filled with grout. Location Johnson City,...

Spokane 115.02 Tunnel

Tasked by Union Pacific Railroad to complete restructuring of tunnel liner with W8 steel sets, then concrete liner, and a shotcrete finish. Client Union Pacific Railroad Company Location Bonners Ferry, Idaho Project Start July 2019 Project Completion November...

Neahkahnie Creek Project/ US HWY 101

Tasked by ODOT to construct a culvert (tunnel) to improve fish habitat and replace a failing 446 ft. long, 6 ft. diameter culvert that ran beneath US HWY 101 in Manzanita, OR. The new culvert consisted of a 204 ft. long, 15 ft. diameter culvert (tunnel), and open cut...

Hardy Tunnel Clearance Improvement Project

The Hardy Tunnel was the 3rd and final tunnel to be completed by LRL in the Altavista District for Norfolk Southern Railway Company. Tasked to improve clearance in this 757’ long, single track tunnel. Liner removal, steel set installation, shotcrete application, and...